JLL's H2 2025 Data Center Report recorded North American primary market vacancy below 1% (1.2% headline, functionally below 1% once LOI and final-negotiation holds are factored in). CBRE's corresponding analysis showed 81.5% of all capacity under construction already preleased (CBRE North America Data Center Figures H2 2025). Cushman and Wakefield's 2025 year-end report confirmed the same pattern across all major metros.
For hyperscalers, this is a logistics problem they solve with 500 MW campus commitments two years in advance. For midmarket operators (the companies deploying 5 to 50 MW of AI inference, private cloud, or GPU compute) it is an existential constraint. You cannot deploy infrastructure in space that does not exist.
The vacancy numbers: what 1% actually means
A 1% vacancy rate in data center markets is not comparable to 1% vacancy in office or industrial real estate. Data center space has much longer procurement and build cycles. When vacancy drops below 3%, available inventory is typically low-quality: wrong power density, wrong location, wrong redundancy tier, or wrong lease terms. At 1%, there is essentially nothing usable on the market.
The 81.5% prelease figure from CBRE is arguably the more important number. It means that of the approximately 5.1 GW of capacity under construction across the US at the end of 2025, roughly 4.16 GW was already committed to tenants before a single rack was installed. The remaining 940 MW of uncommitted capacity under construction will be absorbed within months of delivery, most of it by hyperscalers expanding existing commitments.
Who is taking all the space
The answer is straightforward. Microsoft, Google, Amazon, Meta, and Oracle collectively committed to more than $200 billion in data center capital expenditure through 2026 to 2028 (reported in respective 2025 earnings calls and capital allocation disclosures). These five companies account for an estimated 70 to 80% of new data center leasing activity in primary markets.
This is not new. Hyperscalers have dominated leasing for years. What has changed is the scale. Individual campus commitments now regularly exceed 200 MW, with Microsoft's recent deals in Wisconsin and Georgia each surpassing 500 MW. At that scale, a single tenant can absorb an entire market's new construction pipeline.
That leaves midmarket operators competing for what is left. And there is not much left.
The traditional build timeline problem
Even if a midmarket operator secures land and power entitlements today, the traditional data center build timeline works against them. JLL's 2026 Global Data Center Outlook puts the average build time for a 50 MW data center at 18 months, with 57% of projects running three months or more late in 2025, and that is after permitting, which adds another 6 to 12 months depending on jurisdiction.
The cost picture is equally challenging. Turner and Townsend reported traditional data center construction costs of $10.3 million to $11.3 million per MW of IT load in primary US markets. A 10 MW facility costs $103 million to $113 million before land, utility interconnection, and soft costs. For a midmarket company, that is a significant capital commitment for capacity that will not be available for 2 to 3 years.
Modular infrastructure: the market response
The modular data center market exists because traditional construction cannot keep pace with demand. Grand View Research valued the global modular data center market at $29.03 billion in 2023, projecting growth to $75.77 billion by 2030 at a 17.2% CAGR (Grand View Research, "Modular Data Center Market Size Report," 2024). That growth rate is not driven by preference. It is driven by necessity.
What modular means in practice
The term gets overloaded. Some vendors use it to describe prefabricated power and cooling modules assembled on-site. Others mean fully self-contained data center units shipped in standard containers. The distinction matters because the deployment timelines and cost structures differ significantly.
Compare the traditional figures, which Turner and Townsend publish, with the modular ranges above. The capital gap on those benchmarks is large. The timeline gap is real only when the electrical path was ordered early enough to meet the modules. A factory advertisement is not that order. Traditional builds still offer more site-specific customization. When the buyer needs capacity on a 2026 or 2027 clock, a multi-year ground-up schedule does not answer the question.
Secondary markets: where power and land still exist
The vacancy crisis is concentrated in primary markets. Secondary and tertiary markets tell a different story, not because demand is lower, but because supply has not been as thoroughly consumed.
Case studies: who is already moving
Crusoe Energy: factory-built GPU infrastructure
Crusoe Energy's approach is worth studying. Their Spark Factory in Tyler, Texas produces modular data center units designed specifically for high-density GPU workloads. Rather than building traditional data centers, they manufacture standardized compute modules in a factory environment and deploy them to sites with available power, often in secondary markets where stranded or underused power capacity exists.
The factory model lets Crusoe control quality and timeline in ways that traditional construction cannot. Factory environments have consistent labor, consistent tooling, and the ability to run 24/7 production schedules without weather delays. Crusoe has not disclosed exact unit costs, but the modular approach inherently benefits from manufacturing economics: learning curves, bulk procurement, and parallel production.
LG CNS: modular at enterprise scale
LG CNS entered the US modular data center market in 2024 with a platform designed for 5 to 20 MW deployments. Their approach uses prefabricated power and cooling modules that ship in standard containers. LG CNS has described on-site assembly in 90 to 120 days. That is the vendor's claim, not a measured industry schedule. The platform is described at up to 50 kW per rack with direct liquid cooling, which is a competitive enterprise band and below the cold plate tier used for the densest GPU racks.
What makes LG CNS relevant to midmarket operators specifically is the deployment scale. They are not targeting 200 MW hyperscale campuses. They are targeting the 5 to 20 MW deployments that do not have the capital or timeline for traditional construction but need more than a few racks in a colo facility.
The upper end: cold plate liquid cooling
The modular vertical is not one density band. Air-and-water designs still cluster near 40 kW per rack. Cold plate platforms aimed at GB200, GB300, and Vera Rubin class racks are specified well above that, from about 130 kW into the 250 kW range, with factory-fitted supply and return manifolds and dripless quick-disconnect fittings. That upper tier is the one most traditional retrofit facilities cannot reach.
The cost comparison: traditional versus modular
| Factor | Traditional build | Modular market range |
|---|---|---|
| Capital cost per MW | $10.3 million to $11.3 million | $4 million to $8 million |
| Time to operational (factory plus commissioning) | 18 to 24 months (construction only) | Vendor-advertised. Not a measured ready-for-service date. |
| Total timeline (with permitting) | 27 to 42 months | Set by permits plus the longest electrical item |
| Max power density | Configurable (any) | About 40 kW to 250 kW per rack, by cooling architecture |
| Scalability | Fixed at design capacity | Incremental (add modules) |
| 10 MW total capex | $103 million to $113 million | $40 million to $80 million |
Sources: Turner and Townsend Data Centre Cost Index 2025 (traditional: $10.3 million to $11.3 million per MW). Modular capital figures are published vendor benchmarks (LG CNS, Crusoe Spark Factory, and comparable factory-built platforms) and vary with site conditions, rack density, and cooling. They assume the pad and utility service are already in place or funded separately. Modular timelines in this note are vendor advertisements, not measured ready-for-service dates.
The spread inside that modular range is the part buyers misread. A vendor's place on the cost curve, and any schedule attached to it, is an advertisement. It moves with cooling architecture, density, and how much of the site work is already done. What does not move is the constraint: a factory schedule still waits on the transformer, the interconnect, and a pad that can take the load. The operators who land capacity in a market this tight are the ones who secured power first and treated the module as the increment that matches that power.
The capital efficiency gap is significant. A midmarket operator deploying 10 MW via modular infrastructure typically saves $25 million to $75 million in upfront capital compared to traditional construction, with the exact savings depending on which modular platform is selected and how much of the site work is pre-existing. That freed capital can fund the IT equipment itself, or it can support a phased deployment strategy where you start with 2 MW and scale to 10 MW as demand materializes.
But capital cost is not the whole picture. The time-value of compute matters too. If the traditional path delivers in early 2029, the months between now and then are compute that does not arrive. For a GPU inference provider charging $2 to $4 per GPU hour, a delay of that length on a 10 MW deployment is tens of millions in revenue. The figure is illustrative. It depends on utilization, and it is not a quote.
What this means for 2026 deployment decisions
The data center market has not loosened in 2026. The published reports point the same direction: demand continues to outpace supply, hyperscalers continue to absorb the majority of new capacity, and primary market vacancy stays near zero.
For midmarket operators, the practical playbook looks like this:
The operators deploying successfully in 2026 are not the ones with the biggest budgets. They are the ones who accepted the vacancy reality six months ago, identified secondary market sites with available power, and committed to modular deployment timelines that match when they actually need compute capacity.
Waiting for primary market vacancy to improve is a losing strategy. The math says it will not.