Five year cost, as a range.
Compare a conventional build, colocation and modular data centers for your capacity over five years. Every result is a low to high range from published industry figures, not a single invented number.
Your capacity
IT capacity 1.5 MW (1,500 kW)
Share of IT capacity drawing power on average. Visitor input.
Sets the industry PUE range for the conventional build only. Modular and colocation use the liquid cooled range. PUE figures here are industry ranges, not Syaala figures.
A new line adds the utility study and construction wait to every path: modular, colocation and conventional alike. Idle capital follows from the months on each path.
Facility cost only, over 5 years. IT hardware, staffing, connectivity and financing are excluded for all three paths. Idle capital is shown separately and is not added into the five year cost.
Results, low to high
Modular data centers, five year cost
$9.0M to $18.4M
Capex plus five years of electricity. The headline comparison case.
Five year cost bands
Modular data centers
Capex
$6.0M to $10.5M
Model assumption per MW. Not a Syaala price.
Months to ready for service
4 to 8
Syaala public schedule, from order.
Five year electricity
$3.0M to $7.9M
PUE basis, this path: liquid cooled, 1.15 to 1.25 (industry range).
Idle capital while waiting
$4.8M to $24.0M
GPU capital cost carried during the wait.
Conventional build
Capex
$13.3M to $35.0M
Months to ready for service
18 to 24
Build only. Excludes utility waits.
Five year electricity
$3.0M to $7.9M
PUE basis, this path: your cooling choice (liquid), 1.15 to 1.25 (industry range).
Idle capital while waiting
$21.6M to $72.0M
Colocation
Facility capex
$0
Hosted capacity. No facility capex in this model.
Months to ready for service
4 to 8
By position, from Service Order.
Five year hosting plus electricity
$14.7M to $31.3M
Hosting per kW per month, plus electricity at the tariff range. PUE basis, this path: liquid cooled, 1.15 to 1.25 (industry range).
Idle capital while waiting
$4.8M to $24.0M
Conventional build minus modular data centers, five year cost: -$2.0M to $33.8M
Get this analysis as a PDF.
The report carries the same ranges you see here, with the assumptions and the disclaimer printed in full. No single number is presented as a quotation.
Indicative estimates for planning only. Every result is a range built from the assumptions listed here, which are industry figures and model assumptions, not Syaala prices. They are not a quotation, an offer or financial advice. Actual cost, schedule and returns depend on the site, scope, equipment, financing and market conditions. Syaala prices each project in writing after a site fit.